Active project

Engineering NAS to SharePoint

Moving the whole engineering file share into SharePoint with its structure intact. The first attempt broke the timestamps, so I kept it as an archive, ran a clean migration, and worked every failed file.

The job

The Engineering department’s files lived on a NAS: years of drawings, manuals, configuration files, software and firmware archives, and some very large media and image files. The goal was to move all of it into SharePoint with the same folder structure, so nobody had to relearn where things were on day one.

It was a full migration, not a cleanup, and nothing was allowed to go missing quietly. Every file that didn’t make it had to be accounted for.

The first attempt broke the timestamps

The first approach used a two-way sync. It got the files into SharePoint, but it changed their timestamps on the SharePoint side. The originals on the NAS were fine.

That’s the moment the project changed. The easy move would have been to delete the bad copy and start over. I didn’t.

Keep the bad copy, build a clean one

  • The first copy stayed, marked red. I moved it aside as an archive and color-coded it red, so it was there for comparison or recovery if anything came up.
  • A clean target, marked green. A brand-new destination for the real migration. Red and green meant nobody had to guess which copy was the real one during the switchover.
  • The right tool this time. The main transfer ran through SharePoint Migration Manager, built for exactly this, instead of the sync that caused the problem.

Working the failures

Migration Manager produced detailed scan and failure reports: source, destination, file type, size, and error code for everything it couldn’t move. I treated that report as a work queue, not a footnote.

The failures came in two kinds:

  • Upload failures, mostly very large files: multi-gigabyte archives, disk images, and media.
  • Packaging failures, where the tool couldn’t open a file at all, including some small ones.

32 files were flagged. I moved 30 of them by hand. 2 had content or metadata problems and are still held for review.

Proving it before the switch

Before telling anyone to switch, the new library got tested the way people would actually use it. A colleague opened a CAD file through File Explorer, saved it into SharePoint, reopened it, and checked that the dates and times matched. That was the exact thing the first attempt had broken.

Cutover

  • Early January 2026: the department got notice that the switch was coming that week.
  • January 15, 2026: Engineering moved to SharePoint and stopped using the NAS share for department work. Personal files went to OneDrive.
  • The original archive stayed available until the new library proved itself.

What I took from it

  • A two-way sync isn’t a migration. It can change things you didn’t ask it to change.
  • Keep the failed first attempt. You might need to compare against it, or recover from it.
  • Make the right copy obvious. Red for the archive, green for the real one.
  • A failure report is a to-do list. Every line got worked or explained.
  • Test through the path people actually use. For this team, that was File Explorer and a CAD file, not a browser.
  • “Migrated” isn’t “done.” Naming, permissions, and structure still needed work afterward.

What came next

The migration moved the files. Organizing them is a separate project: a Technical Resources library that merges manuals, firmware, software, and configuration files into one place, organized by system instead of by whoever saved them first. That work is in progress.

Still open

  • The 2 files held for review.
  • When the red archive can be retired.
  • Final total file count and size. I won’t publish a number I haven’t calculated from the reports.