Completed

Moving master control without going off air

Planning a master control relocation and keeping the channel on air through cloud playout while the physical plant moved.

The job

Master control had to move to a new building. The channel couldn’t go dark while it did.

What I did

  • Owned the network side of the move.
  • Helped with the physical move itself: unracking, reracking, and bringing it back online.
  • Kept the channel on air during the move through Harmonic VOS cloud playout, driven by Crispin automation.
  • Set up a monitoring room for cloud master control: four laptops covering viewing, operations, and media file transfers.
  • Brought the master control systems back online in the new building.
  • Afterward, helped redesign the master control networks, defined how they should be built, and fixed what the original integrator install got wrong.

I’m now the primary technical owner for Harmonic VOS and XOS.

Stack

LayerWhat we used
PlayoutHarmonic XOS (on-prem), VOS360 (cloud)
AutomationCrispin Web RPX
ContributionIP streams over SRT
File deliveryAzure file uploads
MonitoringLaptop-based monitoring room during the move

How it flowed

Normal:      Crispin automation → Harmonic XOS (on-prem) → air
During move: Crispin automation → Harmonic VOS360 (cloud) → air
                  ↑ media via Azure uploads, live via SRT
After:       Crispin automation → Harmonic XOS (new building) → air

What I took from it

  • Cloud playout is a real bridge for a move, as long as the media and schedules are staged before you need them.
  • The monitoring room matters as much as the playout. If you can’t see air, you aren’t running it.